BATTERY STORAGE Β· ERCOT

Chocolate Bayou BESS

Chocolate Bayou BESS is a 9.9 MW battery storage request in interconnection study in the ERCOT interconnection queue.

Queue statusIn planning
  1. PlanningQueued Aug 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0583
Grid region
ERCOT (Texas)
Developer
Concurrent Holdco. , LLC.
Connection point (POI)
Station Name: CHOCBAYU _x000D_ Load Name: 38_12_1. Node number 0701._x000D_ Bus #: 80064_x000D_ Voltage: 138 kV
Technology
Battery: 9.9 MW
Total requested
9.9 MW
Study phase
No MRD
Queue status
Active
Entered queue
22 August 2023
Proposed online date
May 2026

Location

No county location in the queue data.

Power plants in Β· Transmission lines in

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem