GAS Β· ERCOTMirage
Mirage is a 11.0 MW gas request suspended in the ERCOT interconnection queue, in Harris County, Texas.
Queue statusPaused / redesign
- PlanningQueued Feb 2015 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- Operating (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 17INR0022
- Grid region
- ERCOT (Texas)
- Location
- Harris County, Texas
- Technology
- Gas: 11.0 MW
- Total requested
- 11.0 MW
- Queue status
- Suspended
- Entered queue
- 16 February 2015
Location
Marker shows the centre of Harris County; the queue data does not give exact sites.
Other requests in Harris County
- Elmax Power StationGas Β· 519 MW Β· agreement signed
- NRG THW GT 345 (Tef)Gas Β· 456 MW Β· agreement signed
- NRG Greens Bayou 6 (TEF-Due Diligence)Gas Β· 445 MW Β· agreement signed
- Rhapsody StorageBattery storage Β· 206 MW Β· agreement signed
- Callisto II Energy CenterBattery storage Β· 203 MW Β· agreement signed
- Brookview Road BESSBattery storage Β· 203 MW Β· agreement signed
- Houston IV BESSBattery storage Β· 165 MW Β· agreement signed
- Dori BQ BESSSolar + storage Β· 154 MW Β· agreement signed
- Friendswood Energy GencoGas Β· 144 MW Β· agreement signed
- Remy Jade III Power StationGas Β· 102 MW Β· agreement signed
- Pamela Heights IBattery storage Β· 102 MW Β· agreement signed
- Megamouth Energy StorageBattery storage Β· 101 MW Β· agreement signed
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem