🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues

OCTARY USA · INTERCONNECTION QUEUES

Interconnection queue in ERCOT (Texas) — page 23

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown1,986447.3 GW
Active in queue447.3 GW1,986 requests
Agreement signed119.3 GW578 requests
Withdrawn1,158262.0 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

1,986 requests · page 23 of 40
ProjectCapacityStatusLocationRegionQueuedOnline
Brazos River BESS
Battery storage · Brazos River BESS LLC
180 MWAgreement signed Brazoria, TXERCOT Oct 2023target 2027
Alliance Solar
Solar
180 MWPaused / redesign Navarro, TXERCOT Jul 2023target 2028
Wildwind
Onshore wind · Wildcat Creek
180 MWAgreement signed Cooke, TXERCOT Oct 20172021
Amberjack2 BESS
Battery storage · Hunt Energy Network, LLC
180 MWIn study Cameron, TXERCOT Jan 2025target 2027
Indigo solar 2
Solar + storage · Indigo Solar 2
180 MWIn study Fisher, TXERCOT Oct 2023target 2027
Whitetail BESS
Battery storage · Hunt Energy Network, LLC
180 MWIn study Mitchell, TXERCOT Feb 2024target 2027
Water Valley Wind Energy
Onshore wind · Water Valley Wind Energy, LLC
180 MWAgreement signed Tom Green, TXERCOT Jan 2019target 2027
Bestla Solar
Solar
180 MWPaused / redesign Winkler, TXERCOT Jan 2017
Proteus Thornton Ranch Solar SLF
Solar + storage · Thornton Ranch Solar, LLC
180 MWIn study Ward, TXERCOT Feb 2024target 2027
Scarlet Solar
Solar · Innovative Solar 416, LLC
180 MWIn study Castro, TXERCOT Dec 2019target 2025
Green Ocelot Storage
Solar + storage · Ocelot Solar LLC
179 MWIn study Kenedy, TXERCOT Jan 2025target 2028
Longfellow Solar I
Solar + storage · CENTURY GAS PROCESSING, LLC
178 MWAgreement signed Pecos, TXERCOT Nov 2022target 2027
Millers Branch Solar II
Solar · Miller's Branch Solar, LLC
178 MWAgreement signed Haskell, TXERCOT Nov 2021target 2026
Tri-County Solar
Solar
178 MWPaused / redesign Crane, TXERCOT Oct 2016
Saddle Horn Station BESS SLF
Solar + storage · Saddle Horn Station BESS LLC
177 MWIn study Comanche, TXERCOT Sep 2024target 2028
Willis Storage
Battery storage · BT Majewski Storage LLC
176 MWAgreement signed Rains, TXERCOT Mar 2023target 2027
McMurtre Storage
Battery storage · BT McMurtre Storage, LLC
176 MWIn study Hunt, TXERCOT Mar 2023target 2027
Brotherton Storage
Battery storage · BT Brotherton Storage, LLC
176 MWAgreement signed Anderson, TXERCOT Apr 2023target 2027
Rowdy Creek BESS
Solar + storage · Rowdy Creek Solar LLC
176 MWAgreement signed Lamar, TXERCOT Jan 2022target 2027
Yooperlite Storage
Battery storage · BT Yooperlite Storage, LLC
176 MWIn study Wise, TXERCOT Jun 2023target 2028
Grandfalls Solar
Solar + storage · Nextera
176 MWAgreement signed Upton, TXERCOT May 2016target 2027
Hackberry Creek Solar
Solar · Hackberry Creek Solar LLC
176 MWAgreement signed Mitchell, TXERCOT Jul 2023target 2028
Sol Marina Energy Center
Solar + storage · Adapture Solar Development, LLC
175 MWAgreement signed Ellis, TXERCOT Oct 2023target 2027
Eligius BESS
Battery storage · Eligius Storage LLC
175 MWIn study Hidalgo, TXERCOT Feb 2025target 2028
Saddle Horn Station Solar SLF
Solar + storage · Saddle Horn Station LLC
175 MWIn study Comanche, TXERCOT Sep 2024target 2028
Coastal Bayou Storage
Battery storage · TOCE TX BESS 5, LLC
175 MWIn study Harris, TXERCOT Sep 2024target 2027
Cold Creek Storage 2
Solar + storage · Cold Creek Solar LLC
174 MWAgreement signed Schleicher, TXERCOT Dec 2023target 2028
Pethrus BESS
Battery storage · Pethrus BESS, LLC
174 MWIn study Wichita, TXERCOT Sep 2023target 2028
Honey Mesquite Wind Farm
Onshore wind · Honey Mesquite Wind Farm , LLC
174 MWAgreement signed Glasscock, TXERCOT Mar 2024target 2026
Bluebonnet Prairie Wind
Onshore wind · Bluebonnet Prairie Wind, LLC
173 MWAgreement signed Navarro, TXERCOT Dec 2022target 2027
Wagon Timber Solar
Solar + storage · Wagon Timber Solar, LLC
172 MWIn study Knox, TXERCOT Dec 2024target 2028
Concho Pearl Solar
Solar + storage · Concho Pearl Solar, LLC
172 MWAgreement signed Concho, TXERCOT Dec 2022target 2027
Cascade Solar
Solar
171 MWPaused / redesign Brazoria, TXERCOT Feb 2021target 2024
Yellow Viking Solar
Solar · Yellow Viking Development One, LLC
171 MWAgreement signed Somervell, TXERCOT Oct 2020target 2027
Coneflower Storage Project
Battery storage · Coneflower Storage Project LLC
171 MWAgreement signed Chambers, TXERCOT Dec 2021target 2027
MRG Goody Solar
Solar + storage · MRG GOODY SOLAR PROJECT, LLC
171 MWAgreement signed Lamar, TXERCOT Mar 2021target 2026
Sullivan Solar
Solar + storage · Sullivan Solar LLC
171 MWIn study Hidalgo, TXERCOT Mar 2024target 2029
Seven Springs Storage
Solar + storage · Hancock Reservoir, LLC
171 MWIn study Lampasas, TXERCOT Apr 2024target 2028
Tokio Solar
Solar · Gransolar Texas Eight, LLC
171 MWAgreement signed Mclennan, TXERCOT Aug 2021target 2027
Fagus Solar Park 3 SLF
Solar + storage · Greenalia Solar Power Misae III, LLC
170 MWAgreement signed Childress, TXERCOT Jun 2024target 2027
Juniperus BESS
Solar + storage · BLUE STONE RENEWABLE XXI LLC
170 MWIn study Hopkins, TXERCOT Oct 2023target 2029
Buffalo Gap 3 Wind Repower
Onshore wind · Buffalo Gap Wind Farm 3, LLC
169 MWAgreement signed Taylor, TXERCOT Dec 2024target 2026
Donna Solar
Solar + storage · Donna Solar LLC
168 MWIn study Hidalgo, TXERCOT Mar 2024target 2029
Carol Battery
Battery storage
168 MWPaused / redesign Potter, TXERCOT Jun 2019
Jalisco Cogen
Gas · HEP Power Generation, LLC
168 MWIn study Nueces, TXERCOT Aug 2024target 2029
Bell Song Solar 2
Solar · Bell Song Solar, LLC 2
168 MWIn study Jim Hogg, TXERCOT Jun 2025target 2030
Bell Song Solar 3
Solar · Bell Song Solar, LLC_3
168 MWIn study Jim Hogg, TXERCOT Jun 2025target 2030
Bell Song Solar
Solar · Bell Song Solar, LLC
168 MWIn study Jim Hogg, TXERCOT Jun 2025target 2029
Fagus Solar Park 2 SLF
Solar + storage · Excel Advantage Services, LLC dba Misae Solar Park II
167 MWAgreement signed Childress, TXERCOT Jun 2024target 2026
Fagus Solar Park 1 SLF
Solar + storage · Excel Advantage Services, LLC dba Misae Solar Park II
166 MWAgreement signed Childress, TXERCOT May 2018target 2026
Page 23 of 40

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)