SOLAR + STORAGE · ERCOTSeven Springs Storage
Seven Springs Storage is a 171 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Lampasas County, Texas.
Queue statusIn planning
- PlanningQueued Apr 2024 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget May 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 26INR0489
- Grid region
- ERCOT (Texas)
- Developer
- Hancock Reservoir, LLC
- Connection point (POI)
- Tap 7061 Copperas Cove to 7260 Kempner 138 kV
- Location
- Lampasas County, Texas
- Technology
- Battery: 171 MW · Battery
- Total requested
- 171 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 9 April 2024
- Proposed online date
- May 2028
Location
Marker shows the centre of Lampasas County; the queue data does not give exact sites.
Other requests in Lampasas County
- Thomas Cameron BESSBattery storage · 202 MW · agreement signed
- Seven Springs SolarSolar + storage · 145 MW · agreement signed
- Barkley Creek SolarSolar · 312 MW · in study
- Aurora Energy StorageBattery storage · 306 MW · in study
- Solgen SolarSolar + storage · 160 MW · in study
- Solgen StorageSolar + storage · 150 MW · in study
- Triple B Solar Alt#2Solar · 150 MW · in study
- Gibson Branch BESSBattery storage · 143 MW · in study
- Hana Springs BESSBattery storage · 101 MW · in study
- Blue Cut SolarSolar · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem