United States › Grid › Interconnection queues › Texas
SOLAR · ERCOTTriple B Solar Alt#2
Triple B Solar Alt#2 is a 150 MW solar request in interconnection study in the ERCOT interconnection queue, in Lampasas County, Texas.
Queue statusIn planning
- PlanningQueued Jun 2021 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jul 2027 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 24INR0069
- Grid region
- ERCOT (Texas)
- Developer
- Triple B Solar LLC
- Connection point (POI)
- Tap 138kV 7066 Adamsville - 7064 Lampasas
- Location
- Lampasas County, Texas
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 10 June 2021
- Proposed online date
- July 2027
Location
Marker shows the centre of Lampasas County; the queue data does not give exact sites.
Other requests in Lampasas County
- Thomas Cameron BESSBattery storage · 202 MW · agreement signed
- Seven Springs SolarSolar + storage · 145 MW · agreement signed
- Barkley Creek SolarSolar · 312 MW · in study
- Aurora Energy StorageBattery storage · 306 MW · in study
- Seven Springs StorageSolar + storage · 171 MW · in study
- Solgen SolarSolar + storage · 160 MW · in study
- Solgen StorageSolar + storage · 150 MW · in study
- Gibson Branch BESSBattery storage · 143 MW · in study
- Hana Springs BESSBattery storage · 101 MW · in study
- Blue Cut SolarSolar · 150 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem