United States βΊ Grid βΊ Interconnection queues βΊ Texas
SOLAR Β· ERCOTBlue Cut Solar
Blue Cut Solar is a 150 MW solar request withdrawn in the ERCOT interconnection queue, in Lampasas County, Texas.
Queue statusWithdrawn / abandoned
- PlanningQueued Jan 2019 (completed)
- Withdrawn / abandonedDec 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- 21INR0254
- Grid region
- ERCOT (Texas)
- Developer
- Blue Cut Solar, LLC
- Connection point (POI)
- tap 138kV 7064 Lampasas - 260 Kempner
- Location
- Lampasas County, Texas
- Technology
- Solar: 150 MW
- Total requested
- 150 MW
- Study phase
- FIS
- Queue status
- Withdrawn
- Entered queue
- 29 January 2019
- Proposed online date
- November 2025
- Withdrawn
- December 2024
Location
Marker shows the centre of Lampasas County; the queue data does not give exact sites.
Other requests in Lampasas County
- Thomas Cameron BESSBattery storage Β· 202 MW Β· agreement signed
- Seven Springs SolarSolar + storage Β· 145 MW Β· agreement signed
- Barkley Creek SolarSolar Β· 312 MW Β· in study
- Aurora Energy StorageBattery storage Β· 306 MW Β· in study
- Seven Springs StorageSolar + storage Β· 171 MW Β· in study
- Solgen SolarSolar + storage Β· 160 MW Β· in study
- Solgen StorageSolar + storage Β· 150 MW Β· in study
- Triple B Solar Alt#2Solar Β· 150 MW Β· in study
- Gibson Branch BESSBattery storage Β· 143 MW Β· in study
- Hana Springs BESSBattery storage Β· 101 MW Β· in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem