United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Hana Springs BESS

Hana Springs BESS is a 101 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Lampasas County, Texas.

Queue statusIn planning
  1. PlanningQueued Nov 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget May 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
24INR0494
Grid region
ERCOT (Texas)
Developer
Black Mountain Energy Storage II LLC
Connection point (POI)
7064 LAMPASAS 138KV
Location
Lampasas County, Texas
Technology
Battery: 101 MW
Total requested
101 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
23 November 2022
Proposed online date
May 2028

Location

Marker shows the centre of Lampasas County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Lampasas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem