United States › Grid › Interconnection queues › Texas
BATTERY STORAGE · ERCOTEligius BESS
Eligius BESS is a 175 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Hidalgo County, Texas.
Queue statusIn planning
- PlanningQueued Feb 2025 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Nov 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0247
- Grid region
- ERCOT (Texas)
- Developer
- Eligius Storage LLC
- Connection point (POI)
- tap 138kV Liston (#8394) – JL Bates (#8392) line, AEP
- Location
- Hidalgo County, Texas
- Technology
- Battery: 175 MW
- Total requested
- 175 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 25 February 2025
- Proposed online date
- November 2028
Location
Marker shows the centre of Hidalgo County; the queue data does not give exact sites.
Other requests in Hidalgo County
- Grapefruit SolarSolar · 291 MW · agreement signed
- Monte Cristo 1 WindOnshore wind · 235 MW · agreement signed
- Monte Cristo II WindOnshore wind · 234 MW · agreement signed
- Gunnar BESSBattery storage · 155 MW · agreement signed
- Carambola BESSBattery storage · 101 MW · agreement signed
- North Edinburg BESS 1Battery storage · 10.0 MW · agreement signed
- SE Edinburg BESSBattery storage · 9.9 MW · agreement signed
- Palmview BESSBattery storage · 9.9 MW · agreement signed
- Val Vista Grid BESS 2Battery storage · 211 MW · in study
- Val Vista Grid BESS 1Battery storage · 209 MW · in study
- McMEXICO STORAGEBattery storage · 202 MW · in study
- Fike BESSBattery storage · 201 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem