United States › Grid › Interconnection queues › Texas
ONSHORE WIND · ERCOTMonte Cristo 1 Wind
Monte Cristo 1 Wind is a 235 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Hidalgo County, Texas.
Queue statusConsented
- PlanningQueued Apr 2017 (completed)
- ConsentedMay 2023 (current stage)
- Construction (not yet reached)
- OperatingTarget Nov 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 19INR0054
- Grid region
- ERCOT (Texas)
- Developer
- Terra-Gen
- Connection point (POI)
- Tap 345kV #8574 Pomelo - #8383 North Edinburg Ckt 2
- Location
- Hidalgo County, Texas
- Technology
- Wind: 235 MW
- Total requested
- 235 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 11 April 2017
- Agreement signed
- 9 May 2023
- Proposed online date
- November 2025
Location
Marker shows the centre of Hidalgo County; the queue data does not give exact sites.
Other requests in Hidalgo County
- Grapefruit SolarSolar · 291 MW · agreement signed
- Monte Cristo II WindOnshore wind · 234 MW · agreement signed
- Gunnar BESSBattery storage · 155 MW · agreement signed
- Carambola BESSBattery storage · 101 MW · agreement signed
- North Edinburg BESS 1Battery storage · 10.0 MW · agreement signed
- SE Edinburg BESSBattery storage · 9.9 MW · agreement signed
- Palmview BESSBattery storage · 9.9 MW · agreement signed
- Val Vista Grid BESS 2Battery storage · 211 MW · in study
- Val Vista Grid BESS 1Battery storage · 209 MW · in study
- McMEXICO STORAGEBattery storage · 202 MW · in study
- Fike BESSBattery storage · 201 MW · in study
- PSE Chihuahua TX StorageBattery storage · 200 MW · in study
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem