BATTERY STORAGE · ERCOT

SE Edinburg BESS

SE Edinburg BESS is a 9.9 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Hidalgo County, Texas.

Queue statusConsented
  1. Planning (completed)
  2. ConsentedApr 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0642
Grid region
ERCOT (Texas)
Developer
SBESS TX16 LLC
Connection point (POI)
Southeast Edinburg, XFMR 2, #6580 CKT, SOUTHEAST EDINBURG, SE_EDINB, Ercot Bus # 8374, Ercot Load name - 138_12_2
Location
Hidalgo County, Texas
Technology
Battery: 9.9 MW
Total requested
9.9 MW
Study phase
IA Executed
Queue status
Active
Agreement signed
26 April 2024
Proposed online date
April 2026

Location

Marker shows the centre of Hidalgo County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hidalgo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem