🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

North Edinburg BESS 1

North Edinburg BESS 1 is a 10.0 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Hidalgo County, Texas.

Queue statusConsented
  1. PlanningQueued May 2025 (completed)
  2. ConsentedJun 2025 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Mar 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
26INR0682
Grid region
ERCOT (Texas)
Developer
Edinburg ESS Assets LLC
Connection point (POI)
TSP Station Name: North Edinburg TSP Station Code: NEDIN Load Name / Load Transformer Name: LOAD3 Bus #: PTI Bus Number: 8380 Voltage (Transmission level kV): 138 kV Node (associated w/ load/load XFMR
Location
Hidalgo County, Texas
Technology
Battery: 10.0 MW
Total requested
10.0 MW
Study phase
MRD Approved
Queue status
Active
Entered queue
22 May 2025
Agreement signed
10 June 2025
Proposed online date
March 2026

Location

Marker shows the centre of Hidalgo County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hidalgo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem