🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Palmview BESS

Palmview BESS is a 9.9 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Hidalgo County, Texas.

Queue statusConsented
  1. Planning (completed)
  2. ConsentedApr 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0628
Grid region
ERCOT (Texas)
Developer
SBESS TX14 LLC
Connection point (POI)
Palmview XFMR 2 CKT 6790 Substation transmission - 138kv ERCOT station code - PALMVIEW PTI Bus # 8387 ERCOT Load Name - LD02
Location
Hidalgo County, Texas
Technology
Battery: 9.9 MW
Total requested
9.9 MW
Study phase
IA Executed
Queue status
Active
Agreement signed
15 April 2024
Proposed online date
April 2026

Location

Marker shows the centre of Hidalgo County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Hidalgo County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem