ONSHORE WIND · ERCOTWildwind
Wildwind is a 180 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Cooke County, Texas.
Queue statusConsented
- PlanningQueued Oct 2017 (completed)
- ConsentedFeb 2020 (current stage)
- Construction (not yet reached)
- OperatingJul 2021 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 20INR0033
- Grid region
- ERCOT (Texas)
- Developer
- Wildcat Creek
- Connection point (POI)
- tap 345kV 1730 KrumW - 2373 Anna
- Location
- Cooke County, Texas
- Technology
- Wind: 180 MW
- Total requested
- 180 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 18 October 2017
- Agreement signed
- 21 February 2020
- Proposed online date
- April 2026
- Came online
- July 2021
Location
Marker shows the centre of Cooke County; the queue data does not give exact sites.
Other requests in Cooke County
- Two Forks BESSBattery storage · 310 MW · agreement signed
- Trojan Solar SLFSolar + storage · 151 MW · agreement signed
- 18-Alpha BESSBattery storage · 307 MW · in study
- Tennuto BESSBattery storage · 202 MW · in study
- Mountain Springs BESSBattery storage · 151 MW · in study
- Backwater StorageBattery storage · 100 MW · suspended
- Backwater SolarSolar · 80.0 MW · suspended
- Rippey SolarSolar · 59.8 MW · built
- Muenster BESSOther · 9.9 MW · built
- Wolf Ridge RepowerOnshore wind · 9.0 MW · built
- Amber StorageOther · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem