ONSHORE WIND · ERCOT

Wildwind

Wildwind is a 180 MW onshore wind request with a signed interconnection agreement in the ERCOT interconnection queue, in Cooke County, Texas.

Queue statusConsented
  1. PlanningQueued Oct 2017 (completed)
  2. ConsentedFeb 2020 (current stage)
  3. Construction (not yet reached)
  4. OperatingJul 2021 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0033
Grid region
ERCOT (Texas)
Developer
Wildcat Creek
Connection point (POI)
tap 345kV 1730 KrumW - 2373 Anna
Location
Cooke County, Texas
Technology
Wind: 180 MW
Total requested
180 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
18 October 2017
Agreement signed
21 February 2020
Proposed online date
April 2026
Came online
July 2021

Location

Marker shows the centre of Cooke County; the queue data does not give exact sites.