United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Two Forks BESS

Two Forks BESS is a 310 MW battery storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Cooke County, Texas.

Queue statusConsented
  1. PlanningQueued Jan 2022 (completed)
  2. ConsentedMay 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Jun 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
24INR0198
Grid region
ERCOT (Texas)
Developer
Two Forks LLC
Connection point (POI)
684 SPRING 138kV
Location
Cooke County, Texas
Technology
Battery: 310 MW
Total requested
310 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
28 January 2022
Agreement signed
3 May 2024
Proposed online date
June 2027

Location

Marker shows the centre of Cooke County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Cooke County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem