United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTTrojan Solar SLF
Trojan Solar SLF is a 151 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Cooke County, Texas.
Queue statusConsented
- PlanningQueued Jul 2021 (completed)
- ConsentedOct 2022 (current stage)
- Construction (not yet reached)
- OperatingTarget May 2026 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- 23INR0296
- Grid region
- ERCOT (Texas)
- Developer
- Compadre Solar, LLC
- Connection point (POI)
- 11735 Cedar Elm Switch 345kV
- Location
- Cooke County, Texas
- Technology
- Solar: 151 MW · Battery
- Total requested
- 151 MW
- Study phase
- SS Completed, FIS Completed, IA
- Queue status
- Active
- Entered queue
- 1 July 2021
- Agreement signed
- 10 October 2022
- Proposed online date
- May 2026
Location
Marker shows the centre of Cooke County; the queue data does not give exact sites.
Other requests in Cooke County
- Two Forks BESSBattery storage · 310 MW · agreement signed
- WildwindOnshore wind · 180 MW · agreement signed
- 18-Alpha BESSBattery storage · 307 MW · in study
- Tennuto BESSBattery storage · 202 MW · in study
- Mountain Springs BESSBattery storage · 151 MW · in study
- Backwater StorageBattery storage · 100 MW · suspended
- Backwater SolarSolar · 80.0 MW · suspended
- Rippey SolarSolar · 59.8 MW · built
- Muenster BESSOther · 9.9 MW · built
- Wolf Ridge RepowerOnshore wind · 9.0 MW · built
- Amber StorageOther · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem