Trojan Solar SLF

Trojan Solar SLF is a 151 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Cooke County, Texas.

Queue statusConsented
  1. PlanningQueued Jul 2021 (completed)
  2. ConsentedOct 2022 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget May 2026 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
23INR0296
Grid region
ERCOT (Texas)
Developer
Compadre Solar, LLC
Connection point (POI)
11735 Cedar Elm Switch 345kV
Location
Cooke County, Texas
Technology
Solar: 151 MW · Battery
Total requested
151 MW
Study phase
SS Completed, FIS Completed, IA
Queue status
Active
Entered queue
1 July 2021
Agreement signed
10 October 2022
Proposed online date
May 2026

Location

Marker shows the centre of Cooke County; the queue data does not give exact sites.