United States › Grid › Interconnection queues › Texas

BATTERY STORAGE · ERCOT

Mountain Springs BESS

Mountain Springs BESS is a 151 MW battery storage request in interconnection study in the ERCOT interconnection queue, in Cooke County, Texas.

Queue statusIn planning
  1. PlanningQueued Oct 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Apr 2027 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
26INR0219
Grid region
ERCOT (Texas)
Developer
Mountain Springs BESS
Connection point (POI)
704 Mountain Springs 138 kV
Location
Cooke County, Texas
Technology
Battery: 151 MW
Total requested
151 MW
Study phase
SS Completed, FIS Completed, No IA
Queue status
Active
Entered queue
4 October 2023
Proposed online date
April 2027

Location

Marker shows the centre of Cooke County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Cooke County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem