United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Concho Pearl Solar

Concho Pearl Solar is a 172 MW solar + storage request with a signed interconnection agreement in the ERCOT interconnection queue, in Concho County, Texas.

Queue statusConsented
  1. PlanningQueued Dec 2022 (completed)
  2. ConsentedJul 2024 (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2027 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
25INR0174
Grid region
ERCOT (Texas)
Developer
Concho Pearl Solar, LLC
Connection point (POI)
Tap 345kV 76009 Twin Buttes - 7077 Amos Creek
Location
Concho County, Texas
Technology
Solar: 172 MW · Battery
Total requested
172 MW
Study phase
SS Completed, FIS Started, IA
Queue status
Active
Entered queue
7 December 2022
Agreement signed
22 July 2024
Proposed online date
October 2027

Location

Marker shows the centre of Concho County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Concho County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem