ONSHORE WIND · ERCOT

Cactus Flats Wind

Cactus Flats Wind is a 148 MW onshore wind request built and operating in the ERCOT interconnection queue, in Concho County, Texas.

Queue statusOperating
  1. PlanningQueued Feb 2015 (completed)
  2. ConsentedMar 2017 (completed)
  3. Construction (completed)
  4. OperatingJun 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
16INR0086
Grid region
ERCOT (Texas)
Developer
Southern Power Company
Connection point (POI)
tap 138kV 6480 SAPS - 6365 Yellow Jacket
Location
Concho County, Texas
Technology
Wind: 148 MW
Total requested
148 MW
Study phase
IA
Queue status
Operational
Entered queue
1 February 2015
Agreement signed
15 March 2017
Proposed online date
June 2022
Came online
June 2022

Location

Marker shows the centre of Concho County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Concho County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem