United States › Grid › Interconnection queues › Texas

SOLAR + STORAGE · ERCOT

Wagon Timber Solar

Wagon Timber Solar is a 172 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Knox County, Texas.

Queue statusIn planning
  1. PlanningQueued Dec 2024 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Oct 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0206
Grid region
ERCOT (Texas)
Developer
Wagon Timber Solar, LLC
Connection point (POI)
6110 Munday East 138kV
Location
Knox County, Texas
Technology
Solar: 172 MW · Battery
Total requested
172 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
19 December 2024
Proposed online date
October 2028

Location

Marker shows the centre of Knox County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Knox County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem