United States › Grid › Interconnection queues › Texas
SOLAR + STORAGE · ERCOTOriole BES
Oriole BES is a 150 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Knox County, Texas.
Queue statusIn planning
- PlanningQueued May 2023 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Dec 2028 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- 28INR0009
- Grid region
- ERCOT (Texas)
- Developer
- Rolling Plains Solar
- Connection point (POI)
- Tap 345kV 6076 Foxtail - 60791 Perigee
- Location
- Knox County, Texas
- Technology
- Battery: 150 MW · Battery
- Total requested
- 150 MW
- Study phase
- SS Completed, FIS Started, No IA
- Queue status
- Active
- Entered queue
- 15 May 2023
- Proposed online date
- December 2028
Location
Marker shows the centre of Knox County; the queue data does not give exact sites.
Other requests in Knox County
- Zeissel SolarSolar · 452 MW · agreement signed
- West Munday WindOnshore wind · 352 MW · agreement signed
- Oriole SolarSolar + storage · 504 MW · in study
- Sundance SolarSolar · 301 MW · in study
- Wagon Timber SolarSolar + storage · 172 MW · in study
- Lemma SolarSolar · 101 MW · in study
- Knox County Moore StorageBattery storage · 77.0 MW · in study
- Wagon Timber StorageSolar + storage · 53.5 MW · in study
- TG East WindOnshore wind · 336 MW · built
- Griffin Trail WindOnshore wind · 226 MW · built
- Vera WindOnshore wind · 209 MW · built
- Vera Wind V110Onshore wind · 34.0 MW · built
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem