ONSHORE WIND · ERCOT

Griffin Trail Wind

Griffin Trail Wind is a 226 MW onshore wind request built and operating in the ERCOT interconnection queue, in Knox County, Texas.

Queue statusOperating
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedMar 2019 (completed)
  3. Construction (completed)
  4. OperatingOct 2021 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
20INR0052
Grid region
ERCOT (Texas)
Developer
Innergex
Connection point (POI)
60506 AVOGADRO 345 kV
Location
Knox County, Texas
Technology
Wind: 226 MW
Total requested
226 MW
Study phase
IA
Queue status
Operational
Entered queue
4 March 2018
Agreement signed
4 March 2019
Proposed online date
October 2021
Came online
October 2021

Location

Marker shows the centre of Knox County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Knox County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem