United States β€Ί Grid β€Ί Interconnection queues β€Ί Texas

ONSHORE WIND Β· ERCOT

TG East Wind

TG East Wind is a 336 MW onshore wind request built and operating in the ERCOT interconnection queue, in Knox County, Texas.

Queue statusOperating
  1. PlanningQueued Apr 2017 (completed)
  2. ConsentedOct 2018 (completed)
  3. Construction (completed)
  4. OperatingDec 2022 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
19INR0052
Grid region
ERCOT (Texas)
Developer
Northrenew
Connection point (POI)
60722 Coulomb 345kV
Location
Knox County, Texas
Technology
Wind: 336 MW
Total requested
336 MW
Study phase
IA
Queue status
Operational
Entered queue
3 April 2017
Agreement signed
22 October 2018
Proposed online date
December 2022
Came online
December 2022

Location

Marker shows the centre of Knox County; the queue data does not give exact sites.

Power plants in Texas Β· Transmission lines in Texas

Other requests in Knox County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem