SOLAR + STORAGE · ERCOT

Oriole Solar

Oriole Solar is a 504 MW solar + storage request in interconnection study in the ERCOT interconnection queue, in Knox County, Texas.

Queue statusIn planning
  1. PlanningQueued May 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
28INR0008
Grid region
ERCOT (Texas)
Developer
Rolling Plains Solar
Connection point (POI)
Tap 345kV 6076 Foxtail - 60791 Perigee
Location
Knox County, Texas
Technology
Solar: 504 MW · Battery
Total requested
504 MW
Study phase
SS Completed, FIS Started, No IA
Queue status
Active
Entered queue
15 May 2023
Proposed online date
December 2028

Location

Marker shows the centre of Knox County; the queue data does not give exact sites.

Power plants in Texas · Transmission lines in Texas

Other requests in Knox County