OCTARY USA · INTERCONNECTION QUEUES

Queue projects under construction in the USA — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown19427.7 GW
Active in queue2,001.0 GW9,187 requests
Agreement signed423.2 GW2,141 requests
Withdrawn24,2054,519.8 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

194 requests · page 2 of 4
ProjectCapacityStatusLocationRegionQueuedOnline
Onshore wind project J866, Tunica County
Onshore wind
200 MWUnder construction Tunica, MSMISO Jun 20172024
Solar project J1087, Scott County
Solar
200 MWUnder construction Scott, MOMISO Mar 2018target 2023
Solar project J1458, Washington County
Solar
200 MWUnder construction Washington, MSMISO Apr 2019target 2024
Solar project J878, Kenosha County
Solar
200 MWUnder construction Kenosha, WIMISO Jun 20172024
Solar project J805, Shelby County
Solar
199 MWUnder construction Shelby, INMISO Jun 2017target 2022
Solar project J1063, Clinton County
Solar
195 MWUnder construction Clinton, INMISO Mar 20182024
Solar project J799, Washtenaw County
Solar
189 MWUnder construction Washtenaw, MIMISO Jun 2017target 2021
Solar project J919, Jackson County
Solar
180 MWUnder construction Jackson, ARMISO Jun 20172023
Onshore wind project J1437, Carroll County
Onshore wind
180 MWUnder construction Carroll, ARMISO Apr 2019target 2024
Gas project 328, Pinellas County
Gas · Duke Energy Florida, LLC
172 MWUnder construction Pinellas, FLSoutheast Jun 2023target 2024
Solar project J1297, Shiawassee County
Solar
170 MWUnder construction Shiawassee, MIMISO Apr 2019target 2024
Solar project J1224, Washtenaw County
Solar
170 MWUnder construction Washtenaw, MIMISO Apr 2019target 2025
Solar project J1174, Worth County
Solar
165 MWUnder construction Worth, IAMISO Mar 2018target 2024
Solar project J1442, Polk County
Solar
165 MWUnder construction Polk, TXMISO Apr 2019target 2025
Solar project J1440, Tunica County
Solar
160 MWUnder construction Tunica, MSMISO Apr 2019target 2024
Solar project J1286, Evangeline Parish County
Solar
150 MWUnder construction Evangeline Parish, LAMISO Apr 2019target 2025
Solar project J1084, Clinton County
Solar
150 MWUnder construction Clinton, IAMISO Mar 2018target 2023
Solar project J875, Lenawee County
Solar
150 MWUnder construction Lenawee, MIMISO Jun 2017target 2022
Solar project J1390, Bartholomew County
Solar
150 MWUnder construction Bartholomew, INMISO Apr 2019target 2025
Battery storage project Q357, Maricopa County
Battery storage
150 MWUnder construction Maricopa, AZWest Sep 2020target 2023
Solar project J1671, Walker County
Solar
150 MWUnder construction Walker, TXMISO Jun 2020target 2025
Solar project J1644, St. Landry Parish County
Solar
150 MWUnder construction St. Landry Parish, LAMISO Jun 2020target 2024
Solar project J1094, Washington County
Solar
150 MWUnder construction Washington, ILMISO Mar 2018target 2024
Solar project J1155, Mississippi County
Solar
150 MWUnder construction Mississippi, ARMISO Mar 20182024
Solar project 18-11071, Larimer County
Solar
150 MWUnder construction Larimer, COWest Nov 2018target 2023
Solar project J1096, Saline County
Solar
150 MWUnder construction Saline, ILMISO Mar 2018target 2024
Onshore wind project J967, Mower County
Onshore wind
150 MWUnder construction Mower, MNMISO Mar 2018target 2023
Solar project J874, Murray County
Solar
150 MWUnder construction Murray, MNMISO Jun 2017target 2024
SR Grady_SR Whigham
Solar
150 MWUnder construction Grady, GASoutheast Aug 2024target 2028
Onshore wind project J750, Morgan County
Onshore wind
150 MWUnder construction Morgan, ILMISO Jun 2017target 2022
Solar project J1072, Mower County
Solar
150 MWUnder construction Mower, MNMISO Mar 2018target 2023
Solar project J859, Cass County
Solar
150 MWUnder construction Cass, ILMISO Jun 2017target 2022
Solar project J1750, Marquette County
Solar
150 MWUnder construction Marquette, MIMISO Apr 2022target 2026
Solar project J818, Jefferson County
Solar
149 MWUnder construction Jefferson, WIMISO Jun 2017target 2022
Solar project J1752, Portage County
Solar
148 MWUnder construction Portage, WIMISO May 2022target 2026
Solar project J1125, Cross County
Solar
135 MWUnder construction Cross, ARMISO Mar 2018target 2023
Solar project J1520, Worth County
Solar
135 MWUnder construction Worth, IAMISO Jun 2020target 2027
Solar project J1203, Genesee County
Solar
125 MWUnder construction Genesee, MIMISO Apr 2019target 2025
Solar project J1310, Jackson County
Solar
125 MWUnder construction Jackson, MIMISO Apr 2019target 2024
Solar project J857, Calhoun County
Solar
125 MWUnder construction Calhoun, MIMISO Jun 2017target 2022
SR Rochelle Solar
Solar
120 MWUnder construction Wilcox, GASoutheast Dec 2021target 2026
SR Norwood Solar
Solar
107 MWUnder construction Warren, GASoutheast May 2023target 2026
Solar project J926, St. Croix County
Solar
101 MWUnder construction St. Croix, WIMISO Jun 2017target 2023
Solar + storage project J1269, Warrick County
Solar + storage
100 MWUnder construction Warrick, INMISO Apr 2019target 2025
Solar project J912, Christian County
Solar
100 MWUnder construction Christian, ILMISO Jun 2017target 2023
Solar project J909, Tangipahoa Parish County
Solar
100 MWUnder construction Tangipahoa Parish, LAMISO Jun 2017target 2022
Solar project J1239, Ouachita Parish County
Solar
100 MWUnder construction Ouachita Parish, LAMISO Apr 2019target 2024
Onshore wind project J855, Grant County
Onshore wind
100 MWUnder construction Grant, WIMISO Jun 20172023
Solar project J1071, Oceana County
Solar
100 MWUnder construction Oceana, MIMISO Mar 2018target 2021
Solar project J680, Ashley County
Solar
100 MWUnder construction Ashley, ARMISO Jul 20162024

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)