🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

OCTARY USA · INTERCONNECTION QUEUES

Withdrawn queue requests in Michigan — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown39070.5 GW
Active in queue58.6 GW305 requests
Agreement signed4,949 MW37 requests
Withdrawn39070.5 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

390 requests · page 2 of 8
ProjectCapacityStatusLocationRegionQueuedOnline
Covert Generating Facility
Gas
285 MWWithdrawn / abandoned Van Buren, MIPJM Mar 2018target 2023
Other project G216 CONS 110, Livingston County
Other
280 MWWithdrawn / abandoned Livingston, MIMISO Nov 2001target 2004
Battery storage project J3537, Kalamazoo County
Battery storage
265 MWWithdrawn / abandoned Kalamazoo, MIMISO Apr 2024target 2028
Onshore wind project J546, Huron County
Onshore wind
260 MWWithdrawn / abandoned Huron, MIMISO Mar 2016target 2018
Onshore wind project J1048, Mecosta County
Onshore wind
250 MWWithdrawn / abandoned Mecosta, MIMISO Mar 2018target 2020
Solar + storage project J3769, Saginaw County
Solar + storage
250 MWWithdrawn / abandoned Saginaw, MIMISO Apr 2024target 2028
Solar + storage project J2732, Ogemaw County
Solar + storage
250 MWWithdrawn / abandoned Ogemaw, MIMISO Sep 2022target 2025
Onshore wind project J1077, Cass County
Onshore wind
250 MWWithdrawn / abandoned Cass, MIMISO Mar 2018target 2020
Gas project J413, Marquette County
Gas
243 MWWithdrawn / abandoned Marquette, MIMISO Nov 2014target 2017
Solar + storage project J2617, Van Buren County
Solar + storage
240 MWWithdrawn / abandoned Van Buren, MIMISO Sep 2022target 2026
Gas project J444, Wayne County
Gas
235 MWWithdrawn / abandoned Wayne, MIMISO May 2015target 2017
Gas project J271, Montcalm County
Gas
232 MWWithdrawn / abandoned Montcalm, MIMISO Mar 2013
Battery storage project J3647, Gratiot County
Battery storage
220 MWWithdrawn / abandoned Gratiot, MIMISO Apr 2024target 2028
Gas project J398, Marquette County
Gas
204 MWWithdrawn / abandoned Marquette, MIMISO Sep 2014
Onshore wind project J307, Osceola County
Onshore wind
201 MWWithdrawn / abandoned Osceola, MIMISO Nov 2013
Onshore wind project J579, Allegan County
Onshore wind
200 MWWithdrawn / abandoned Allegan, MIMISO Jun 2017target 2018
Onshore wind project G750, Marquette County
Onshore wind
200 MWWithdrawn / abandoned Marquette, MIMISO Feb 2007target 2009
Solar project J1911, Livingston County
Solar
200 MWWithdrawn / abandoned Livingston, MIMISO Aug 2021target 2023
Solar project J2934, Saginaw County
Solar
200 MWWithdrawn / abandoned Saginaw, MIMISO Sep 2022target 2025
Solar project J1543, Grand Traverse County
Solar
200 MWWithdrawn / abandoned Grand Traverse, MIMISO Jun 2020target 2023
Solar project J1912, Sanilac County
Solar
200 MWWithdrawn / abandoned Sanilac, MIMISO Aug 2021target 2023
Onshore wind project J602, Shiawassee County
Onshore wind
200 MWWithdrawn / abandoned Shiawassee, MIMISO May 2016target 2021
Onshore wind project G937, Delta County
Onshore wind
200 MWWithdrawn / abandoned Delta, MIMISO Dec 2007target 2010
Solar project J1913, Midland County
Solar
200 MWWithdrawn / abandoned Midland, MIMISO Aug 2021target 2023
Battery storage project J3258, Ottawa County
Battery storage
200 MWWithdrawn / abandoned Ottawa, MIMISO Apr 2024target 2028
Solar project J1403, Ionia County
Solar
200 MWWithdrawn / abandoned Ionia, MIMISO Apr 2019target 2023
Solar project J2933, Bay County
Solar
200 MWWithdrawn / abandoned Bay, MIMISO Sep 2022target 2025
Solar project J1526, St. Clair County
Solar
200 MWWithdrawn / abandoned St. Clair, MIMISO Jun 2020target 2026
Battery storage project J3320, Ottawa County
Battery storage
200 MWWithdrawn / abandoned Ottawa, MIMISO Apr 2024target 2028
Onshore wind project J176, Gratiot County
Onshore wind
200 MWWithdrawn / abandoned Gratiot, MIMISO Nov 2010
Onshore wind project J1065, Gratiot County
Onshore wind
200 MWWithdrawn / abandoned Gratiot, MIMISO Mar 2018target 2020
Solar project J1515, Midland County
Solar
200 MWWithdrawn / abandoned Midland, MIMISO Jun 2020target 2023
Onshore wind project J632, Berrien County
Onshore wind
200 MWWithdrawn / abandoned Berrien, MIMISO Jun 2017target 2018
Solar project J1661, Lapeer County
Solar
200 MWWithdrawn / abandoned Lapeer, MIMISO Jun 2020target 2023
Onshore wind project V4-016, Cass County
Onshore wind
200 MWWithdrawn / abandoned Cass, MIPJM Nov 2009target 2014
Solar + storage project J2056, Lenawee County
Solar + storage
200 MWWithdrawn / abandoned Lenawee, MIMISO Aug 2021target 2025
Onshore wind project J203, Sanilac County
Onshore wind
200 MWWithdrawn / abandoned Sanilac, MIMISO Jun 2017target 2012
Solar project J1905, Sanilac County
Solar
200 MWWithdrawn / abandoned Sanilac, MIMISO Aug 2021target 2023
Solar + storage project J3649, Houghton County
Solar + storage
200 MWWithdrawn / abandoned Houghton, MIMISO Apr 2024target 2028
Battery storage project J3786, Washtenaw County
Battery storage
200 MWWithdrawn / abandoned Washtenaw, MIMISO Apr 2024target 2028
Onshore wind project J408, Sanilac County
Onshore wind
200 MWWithdrawn / abandoned Sanilac, MIMISO Nov 2014target 2018
Solar project J2674, Clinton County
Solar
200 MWWithdrawn / abandoned Clinton, MIMISO Sep 2022target 2025
Onshore wind project J537, Sanilac County
Onshore wind
200 MWWithdrawn / abandoned Sanilac, MIMISO Nov 2015target 2017
Onshore wind project J195, Shiawassee County
Onshore wind
200 MWWithdrawn / abandoned Shiawassee, MIMISO Feb 2011target 2012
Onshore wind project J1667, Isabella County
Onshore wind
200 MWWithdrawn / abandoned Isabella, MIMISO Jun 2020target 2023
Solar project J1522, Muskegon County
Solar
200 MWWithdrawn / abandoned Muskegon, MIMISO Jun 2020target 2023
Onshore wind project J222, Gratiot County
Onshore wind
200 MWWithdrawn / abandoned Gratiot, MIMISO Aug 2011target 2014
Solar project J1556, Ottawa County
Solar
200 MWWithdrawn / abandoned Ottawa, MIMISO Jun 2020target 2023
Onshore wind project J170, Tuscola County
Onshore wind
200 MWWithdrawn / abandoned Tuscola, MIMISO Sep 2010target 2011
Battery storage project J3486, Muskegon County
Battery storage
200 MWWithdrawn / abandoned Muskegon, MIMISO Apr 2024target 2028

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)