Onshore wind project J222, Gratiot County

Onshore wind project J222, Gratiot County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Gratiot County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Aug 2011 (completed)
  2. Withdrawn / abandonedAug 2012 (project stopped here)
  3. ConsentedAug 2012 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J222
Grid region
MISO (Midcontinent)
Connection point (POI)
METC Nelson Road - Goss 345 kV
Location
Gratiot County, Michigan
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Feasibility
Queue status
Withdrawn
Entered queue
22 August 2011
Agreement signed
13 August 2012
Proposed online date
December 2014
Withdrawn
August 2012

Location

Marker shows the centre of Gratiot County; the queue data does not give exact sites.