United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

ONSHORE WIND Β· MISO

Onshore wind project J408, Sanilac County

Onshore wind project J408, Sanilac County is a 200 MW onshore wind request withdrawn in the MISO interconnection queue, in Sanilac County, Michigan.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Nov 2014 (completed)
  2. Withdrawn / abandonedJun 2016 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J408
Grid region
MISO (Midcontinent)
Connection point (POI)
Banner 345 kV substation
Location
Sanilac County, Michigan
Technology
Wind: 200 MW
Total requested
200 MW
Study phase
Int FaS
Queue status
Withdrawn
Entered queue
14 November 2014
Proposed online date
September 2018
Withdrawn
June 2016

Location

Marker shows the centre of Sanilac County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Sanilac County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem