United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

SOLAR + STORAGE Β· MISO

Solar + storage project J2732, Ogemaw County

Solar + storage project J2732, Ogemaw County is a 250 MW solar + storage request withdrawn in the MISO interconnection queue, in Ogemaw County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2732
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Gallagher to Twinning 138kV
Location
Ogemaw County, Michigan
Technology
Solar: 250 MW Β· Battery
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
December 2025
Withdrawn
August 2025

Location

Marker shows the centre of Ogemaw County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Ogemaw County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem