United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

SOLAR + STORAGE Β· MISO

Solar + storage project J2617, Van Buren County

Solar + storage project J2617, Van Buren County is a 240 MW solar + storage request withdrawn in the MISO interconnection queue, in Van Buren County, Michigan, connecting to METC.

Queue statusWithdrawn / abandoned
  1. PlanningQueued Sep 2022 (completed)
  2. Withdrawn / abandonedAug 2025 (project stopped here)
  3. Consented (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J2617
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
Palisades to Argenta 345 kV
Location
Van Buren County, Michigan
Technology
Solar: 240 MW Β· Battery
Total requested
240 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 2; Post GIA Status: Not Started
Queue status
Withdrawn
Entered queue
15 September 2022
Proposed online date
September 2026
Withdrawn
August 2025

Location

Marker shows the centre of Van Buren County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Van Buren County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem