BATTERY STORAGE · MISO

Battery storage project J2100, Van Buren County

Battery storage project J2100, Van Buren County is a 250 MW battery storage request in interconnection study in the MISO interconnection queue, in Van Buren County, Michigan, connecting to METC.

Queue statusIn planning
  1. PlanningQueued Aug 2021 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2024 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2100
Grid region
MISO (Midcontinent)
Utility / transmission owner
METC
Connection point (POI)
ARGENTA - PALISADES 345.0kV
Location
Van Buren County, Michigan
Technology
Battery: 250 MW
Total requested
250 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Active
Entered queue
13 August 2021
Proposed online date
September 2024

Location

Marker shows the centre of Van Buren County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Van Buren County