Queue projects under construction in MISO (Midcontinent) — page 2

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown12219.8 GW
Active in queue350.1 GW1,646 requests
Agreement signed28.1 GW187 requests
Withdrawn3,261621.9 GW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

122 requests · page 2 of 3
ProjectCapacityStatusLocationRegionQueuedOnline
Solar project J1442, Polk County
Solar
165 MWUnder construction Polk, TXMISO Apr 2019target 2025
Solar project J1440, Tunica County
Solar
160 MWUnder construction Tunica, MSMISO Apr 2019target 2024
Solar project J1286, Evangeline Parish County
Solar
150 MWUnder construction Evangeline Parish, LAMISO Apr 2019target 2025
Solar project J1084, Clinton County
Solar
150 MWUnder construction Clinton, IAMISO Mar 2018target 2023
Solar project J875, Lenawee County
Solar
150 MWUnder construction Lenawee, MIMISO Jun 2017target 2022
Solar project J1390, Bartholomew County
Solar
150 MWUnder construction Bartholomew, INMISO Apr 2019target 2025
Solar project J1671, Walker County
Solar
150 MWUnder construction Walker, TXMISO Jun 2020target 2025
Solar project J1644, St. Landry Parish County
Solar
150 MWUnder construction St. Landry Parish, LAMISO Jun 2020target 2024
Solar project J1094, Washington County
Solar
150 MWUnder construction Washington, ILMISO Mar 2018target 2024
Solar project J1155, Mississippi County
Solar
150 MWUnder construction Mississippi, ARMISO Mar 20182024
Solar project J1096, Saline County
Solar
150 MWUnder construction Saline, ILMISO Mar 2018target 2024
Onshore wind project J967, Mower County
Onshore wind
150 MWUnder construction Mower, MNMISO Mar 2018target 2023
Solar project J874, Murray County
Solar
150 MWUnder construction Murray, MNMISO Jun 2017target 2024
Onshore wind project J750, Morgan County
Onshore wind
150 MWUnder construction Morgan, ILMISO Jun 2017target 2022
Solar project J1072, Mower County
Solar
150 MWUnder construction Mower, MNMISO Mar 2018target 2023
Solar project J859, Cass County
Solar
150 MWUnder construction Cass, ILMISO Jun 2017target 2022
Solar project J1750, Marquette County
Solar
150 MWUnder construction Marquette, MIMISO Apr 2022target 2026
Solar project J818, Jefferson County
Solar
149 MWUnder construction Jefferson, WIMISO Jun 2017target 2022
Solar project J1752, Portage County
Solar
148 MWUnder construction Portage, WIMISO May 2022target 2026
Solar project J1125, Cross County
Solar
135 MWUnder construction Cross, ARMISO Mar 2018target 2023
Solar project J1520, Worth County
Solar
135 MWUnder construction Worth, IAMISO Jun 2020target 2027
Solar project J1203, Genesee County
Solar
125 MWUnder construction Genesee, MIMISO Apr 2019target 2025
Solar project J1310, Jackson County
Solar
125 MWUnder construction Jackson, MIMISO Apr 2019target 2024
Solar project J857, Calhoun County
Solar
125 MWUnder construction Calhoun, MIMISO Jun 2017target 2022
Solar project J926, St. Croix County
Solar
101 MWUnder construction St. Croix, WIMISO Jun 2017target 2023
Solar + storage project J1269, Warrick County
Solar + storage
100 MWUnder construction Warrick, INMISO Apr 2019target 2025
Solar project J912, Christian County
Solar
100 MWUnder construction Christian, ILMISO Jun 2017target 2023
Solar project J909, Tangipahoa Parish County
Solar
100 MWUnder construction Tangipahoa Parish, LAMISO Jun 2017target 2022
Solar project J1239, Ouachita Parish County
Solar
100 MWUnder construction Ouachita Parish, LAMISO Apr 2019target 2024
Onshore wind project J855, Grant County
Onshore wind
100 MWUnder construction Grant, WIMISO Jun 20172023
Solar project J1071, Oceana County
Solar
100 MWUnder construction Oceana, MIMISO Mar 2018target 2021
Solar project J680, Ashley County
Solar
100 MWUnder construction Ashley, ARMISO Jul 20162024
Solar project J1375, Muskegon County
Solar
100 MWUnder construction Muskegon, MIMISO Apr 2019target 2025
Solar project J1445, Benton County
Solar
100 MWUnder construction Benton, MNMISO Apr 2019target 2025
Solar project J1314, Polk County
Solar
100 MWUnder construction Polk, WIMISO Apr 2019target 2025
Battery storage project J1659, Washtenaw County
Battery storage
100 MWUnder construction Washtenaw, MIMISO Jun 2020target 2025
Solar project J1219, Tangipahoa Parish County
Solar
100 MWUnder construction Tangipahoa Parish, LAMISO Apr 2019target 2024
Solar project J1124, Olmsted County
Solar
100 MWUnder construction Olmsted, MNMISO Mar 2018target 2024
Solar project J1426, Benton County
Solar
100 MWUnder construction Benton, MNMISO Apr 2019target 2025
Solar project J962, Desoto County
Solar
100 MWUnder construction Desoto, MSMISO Mar 20182024
Solar project J903, Henry County
Solar
100 MWUnder construction Henry, INMISO Jun 2017target 2023
Solar project J1131, Scott County
Solar
100 MWUnder construction Scott, IAMISO Mar 2018target 2024
Solar project J1251, Marquette County
Solar
100 MWUnder construction Marquette, MIMISO Apr 2019target 2025
Solar project J1171, Dodge County
Solar
100 MWUnder construction Dodge, WIMISO Mar 20182024
Solar project J1514, Mississippi County
Solar
100 MWUnder construction Mississippi, ARMISO Dec 20212024
Solar project J908, Tallahatchie County
Solar
100 MWUnder construction Tallahatchie, MSMISO Jun 2017target 2023
Solar project J871, Grant County
Solar
100 MWUnder construction Grant, WIMISO Jun 20172023
Onshore wind project J898, Howard County
Onshore wind
100 MWUnder construction Howard, IAMISO Jun 2017target 2023
Solar project J1294, Sunflower County
Solar
99.0 MWUnder construction Sunflower, MSMISO Apr 20192024
Solar project J1144, Covington County
Solar
96.0 MWUnder construction Covington, MSMISO Mar 2018target 2022

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines · Planned power plants (EIA)