United States β€Ί Grid β€Ί Interconnection queues

OCTARY USA Β· INTERCONNECTION QUEUES

Other interconnection queue in the USA (2022 requests)

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown5011.9 GW
Active in queue11.9 GW50 requests
Agreement signed852 MW6 requests
Withdrawn489,713 MW never built

Map

Loading requests…
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

50 requests
ProjectCapacityStatusLocationRegionQueuedOnline
Southeast Oklahoma Pumped Storage
Other Β· Apex Energy Solutions, LLC
1,232 MWIn study Lamar, TXERCOT Aug 2022target 2030
Other project G0787, Wasco County
Other
1,200 MWIn study Wasco, ORWest Aug 2022target 2028
Other project 635, Gooding County
Other Β· Taurus Wind LLC
1,000 MWPaused / redesign Gooding, IDWest Feb 2022target 2029
Replacing 710 MW of coal generation with solar at Sherco Unit 2; Sherco Unit 2
Other
710 MWIn study Sherburne, MNMISO Dec 20222024
Other project G0806, Douglas County
Other
600 MWIn study Douglas, ORWest Sep 2022target 2028
Other project G0811, Lane County
Other
600 MWIn study Lane, ORWest Sep 2022target 2030
Other project G0768, Gilliam County
Other
600 MWIn study Gilliam, ORWest Aug 2022target 2027
Other project J2694, Christian County
Other
500 MWIn study Christian, ILMISO Sep 2022target 2027
Other project J2171, Perry County
Other
500 MWIn study Perry, ILMISO Mar 2022target 2024
Other project J3163, Cass County
Other
479 MWIn study Cass, NDMISO Jul 2022target 2028
Replacing 300 MW of existing coal generation with BESS; Edgewater 5
Other
423 MWIn study MISO Feb 2022target 2025
Other project Q91, Los Angeles County
Other
346 MWIn study Los Angeles, CAWest Jun 2022target 2030
Other project CLPT G17, Laramie County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Laramie, WYWest Apr 2022target 2025
Other project CLPT G16, Platte County
Other Β· NextEra Energy Resources Interconnection Holdings, LLC
300 MWAgreement signed Platte, WYWest Apr 2022target 2025
Other project 112, Apache County
Other
250 MWIn study Apache, AZWest Jan 2022target 2025
Other project J2691, Bollinger County
Other
250 MWIn study Bollinger, MOMISO Sep 2022target 2027
Other project GEN-2022-010, Williams County
Other
250 MWIn study Williams, NDSPP May 20222025
Replacing 30 MW of existing coal generation with BESS at Burlington Generation Station; Burlington 5
Other
212 MWIn study Des Moines, IAMISO Feb 2022target 2024
Other project G0794, Linn County
Other
160 MWIn study Linn, ORWest Aug 2022target 2028
Other project G0793, Linn County
Other
160 MWIn study Linn, ORWest Aug 2022target 2028
Surplus; J734
Other
135 MWIn study Mclean, ILMISO Dec 2022target 2026
Other project GEN-2022-009, Williams County
Other
125 MWIn study Williams, NDSPP May 20222025
Replacing 124.4 MW of existing gas generation with solar at Woodruff County (formerly Bailey); Woodruff Co Solar
Other
124 MWIn study MISO Feb 20222024
Surplus; J947
Other
100 MWIn study MISO Apr 2022target 2023
Surplus; Polaris Solar
Other
100 MWAgreement signed Gratiot, MIMISO Apr 2022target 2023
Other project 115, Pima County
Other
100 MWIn study Pima, AZWest Mar 2022target 2025
Surplus; J1314
Other
100 MWIn study Polk, WIMISO Sep 2022target 2025
Other project 116, Pima County
Other
100 MWIn study Pima, AZWest Mar 2022target 2025
Surplus; J728
Other
90.0 MWIn study Isabella, MIMISO Aug 2022target 2025
Surplus; J717
Other
90.0 MWIn study Isabella, MIMISO Aug 2022target 2025
Surplus; Pine River Solar
Other
80.0 MWAgreement signed Gratiot, MIMISO Apr 2022target 2023
Surplus; J986
Other
75.0 MWIn study MISO Apr 2022target 2022
Surplus; J1067
Other
60.0 MWIn study White, INMISO May 20222024
Surplus; J928
Other
55.0 MWIn study Delta, MIMISO Apr 2022target 2025
Surplus; J1369
Other
50.0 MWAgreement signed Dubois, INMISO May 2022target 2022
Surplus; J1002
Other
50.0 MWIn study Waushara, WIMISO May 2022target 2023
Surplus; J1386
Other
50.0 MWIn study Lake, INMISO May 2022target 2028
Surplus; Gratiot Solar
Other
50.0 MWIn study MISO Apr 2022target 2023
Surplus; Merricourt Solar
Other
49.9 MWIn study MISO Mar 2022target 2028
Other project J2276, Douglas County
Other
39.5 MWIn study Douglas, MNMISO Apr 2022target 2022
Replacing 37 MW of natural gas generation with BESS at Joppa; Joppa
Other
37.0 MWIn study MISO Dec 2022target 2024
Surplus; J1304
Other
33.0 MWIn study Rock, WIMISO Aug 2022target 2023
Surplus; J1188
Other
25.0 MWIn study Rock, WIMISO May 2022target 2022
Surplus; J1000
Other
25.0 MWIn study Grant, WIMISO May 2022target 2023
Surplus; J1305
Other
25.0 MWIn study Green, WIMISO Aug 2022target 2023
Surplus; J864
Other
25.0 MWIn study MISO Apr 2022target 2022
Other project GEN-2023-SR1, Brown County
Other
21.9 MWAgreement signed Brown, NESPP Dec 20222024
Other project AI2-025, New Castle County
Other
10.0 MWIn study New Castle, DEPJM Dec 2022target 2026
Other project AI1-053, Mercer County
Other
6.6 MWIn study Mercer, PAPJM Jun 2022target 2022
Surplus; Petersburg
Other
3.0 MWIn study Pike, INMISO May 2022target 2023

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines Β· Planned power plants (EIA)