United States βΊ Grid βΊ Interconnection queues
OTHER Β· MISOSurplus; J864
Surplus; J864 is a 25.0 MW other request in interconnection study in the MISO interconnection queue, connecting to AMERICAN TRANSMISSION COMPANY.
Queue statusIn planning
- PlanningQueued Apr 2022 (current stage)
- Consented (not yet reached)
- Construction (not yet reached)
- OperatingTarget Jun 2022 (not yet reached)
- Closed (not yet reached)
Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.
Request details
- Queue ID
- S1016
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- AMERICAN TRANSMISSION COMPANY
- Connection point (POI)
- Lone Rock 69kV
- Technology
- Other: 25.0 MW Β· Battery
- Total requested
- 25.0 MW
- Queue status
- Active
- Entered queue
- 15 April 2022
- Proposed online date
- June 2022
Location
No county location in the queue data.
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem