🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Minnesota

OTHER · MISO

Other project J2276, Douglas County

Other project J2276, Douglas County is a 39.5 MW other request in interconnection study in the MISO interconnection queue, in Douglas County, Minnesota, connecting to MISSOURI RIVER ENERGY SERVICES - TRANSMISSION.

Queue statusIn planning
  1. PlanningQueued Apr 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Jan 2022 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
J2276
Grid region
MISO (Midcontinent)
Utility / transmission owner
MISSOURI RIVER ENERGY SERVICES - TRANSMISSION
Connection point (POI)
ALEXANDRIA
Location
Douglas County, Minnesota
Technology
Solar: 39.5 MW · Wind
Total requested
39.5 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: DPP 3; Post GIA Status: Not Started
Queue status
Active
Entered queue
11 April 2022
Proposed online date
January 2022

Location

Marker shows the centre of Douglas County; the queue data does not give exact sites.

Power plants in Minnesota · Transmission lines in Minnesota

Other requests in Douglas County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem