United States › Grid › Interconnection queues › Michigan

OTHER · MISO

Surplus; J928

Surplus; J928 is a 55.0 MW other request in interconnection study in the MISO interconnection queue, in Delta County, Michigan, connecting to AMERICAN TRANSMISSION COMPANY.

Queue statusIn planning
  1. PlanningQueued Apr 2022 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Nov 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
S1015
Grid region
MISO (Midcontinent)
Utility / transmission owner
AMERICAN TRANSMISSION COMPANY
Connection point (POI)
Garden Corners 138kV
Location
Delta County, Michigan
Technology
Solar: 55.0 MW · Other
Total requested
55.0 MW
Queue status
Active
Entered queue
11 April 2022
Proposed online date
November 2025

Location

Marker shows the centre of Delta County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Delta County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem