🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Michigan

SOLAR · MISO

Solar project J1183, Delta County

Solar project J1183, Delta County is a 1.4 MW solar request built and operating in the MISO interconnection queue, in Delta County, Michigan, connecting to American Transmission Co..

Queue statusOperating
  1. PlanningQueued Mar 2018 (completed)
  2. ConsentedApr 2021 (completed)
  3. Construction (completed)
  4. OperatingOct 2019 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
J1183
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Heritage Garden substation
Location
Delta County, Michigan
Technology
Solar: 1.4 MW
Total requested
1.4 MW
Service type
Energy only (ERIS)
Study phase
Study Phase: GIA; Post GIA Status: In Service
Queue status
Operational
Entered queue
12 March 2018
Agreement signed
2 April 2021
Proposed online date
October 2019
Came online
October 2019

Location

Marker shows the centre of Delta County; the queue data does not give exact sites.

Power plants in Michigan · Transmission lines in Michigan

Other requests in Delta County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem