United States › Grid › Interconnection queues › Michigan
SOLAR · MISOSolar project J1183, Delta County
Solar project J1183, Delta County is a 1.4 MW solar request built and operating in the MISO interconnection queue, in Delta County, Michigan, connecting to American Transmission Co..
Request details
- Queue ID
- J1183
- Grid region
- MISO (Midcontinent)
- Utility / transmission owner
- American Transmission Co.
- Connection point (POI)
- Heritage Garden substation
- Location
- Delta County, Michigan
- Technology
- Solar: 1.4 MW
- Total requested
- 1.4 MW
- Service type
- Energy only (ERIS)
- Study phase
- Study Phase: GIA; Post GIA Status: In Service
- Queue status
- Operational
- Entered queue
- 12 March 2018
- Agreement signed
- 2 April 2021
- Proposed online date
- October 2019
- Came online
- October 2019
Location
Marker shows the centre of Delta County; the queue data does not give exact sites.
Other requests in Delta County
- Solar project J2678, Delta CountySolar · 150 MW · in study
- Surplus; J928Other · 55.0 MW · in study
- Onshore wind project J928, Delta CountyOnshore wind · 80.0 MW · built
- Onshore wind project J060, Delta CountyOnshore wind · 29.0 MW · built
- Solar project J557, Delta CountySolar · 0.9 MW · built
- Onshore wind project G937, Delta CountyOnshore wind · 200 MW · withdrawn
- Coal project G567, Delta CountyCoal · 165 MW · withdrawn
- Coal project G568, Delta CountyCoal · 135 MW · withdrawn
- Solar project J849, Delta CountySolar · 125 MW · withdrawn
- Onshore wind project J061, Delta CountyOnshore wind · 70.0 MW · withdrawn
- Other project J039, Delta CountyOther · 50.0 MW · withdrawn
- Onshore wind project J592, Delta CountyOnshore wind · 48.3 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem