United States βΊ Grid βΊ Interconnection queues βΊ Michigan
ONSHORE WIND Β· MISOOnshore wind project J592, Delta County
Onshore wind project J592, Delta County is a 48.3 MW onshore wind request withdrawn in the MISO interconnection queue, in Delta County, Michigan.
Queue statusWithdrawn / abandoned
- PlanningQueued May 2016 (completed)
- Withdrawn / abandonedJul 2017 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- J592
- Grid region
- MISO (Midcontinent)
- Connection point (POI)
- Garden Corners 138kV Substation
- Location
- Delta County, Michigan
- Technology
- Wind: 48.3 MW
- Total requested
- 48.3 MW
- Study phase
- GIA
- Queue status
- Withdrawn
- Entered queue
- 9 May 2016
- Proposed online date
- July 2018
- Withdrawn
- July 2017
Location
Marker shows the centre of Delta County; the queue data does not give exact sites.
Other requests in Delta County
- Solar project J2678, Delta CountySolar Β· 150 MW Β· in study
- Surplus; J928Other Β· 55.0 MW Β· in study
- Onshore wind project J928, Delta CountyOnshore wind Β· 80.0 MW Β· built
- Onshore wind project J060, Delta CountyOnshore wind Β· 29.0 MW Β· built
- Solar project J1183, Delta CountySolar Β· 1.4 MW Β· built
- Solar project J557, Delta CountySolar Β· 0.9 MW Β· built
- Onshore wind project G937, Delta CountyOnshore wind Β· 200 MW Β· withdrawn
- Coal project G567, Delta CountyCoal Β· 165 MW Β· withdrawn
- Coal project G568, Delta CountyCoal Β· 135 MW Β· withdrawn
- Solar project J849, Delta CountySolar Β· 125 MW Β· withdrawn
- Onshore wind project J061, Delta CountyOnshore wind Β· 70.0 MW Β· withdrawn
- Other project J039, Delta CountyOther Β· 50.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem