United States β€Ί Grid β€Ί Interconnection queues β€Ί Michigan

SOLAR Β· MISO

Solar project J849, Delta County

Solar project J849, Delta County is a 125 MW solar request withdrawn in the MISO interconnection queue, in Delta County, Michigan, connecting to American Transmission Co..

Queue statusWithdrawn / abandoned
  1. PlanningQueued Jun 2017 (completed)
  2. Withdrawn / abandonedApr 2022 (project stopped here)
  3. ConsentedJun 2019 (not reached)
  4. Construction (not reached)
  5. Operating (not reached)
  6. Closed (not reached)

Request details

Queue ID
J849
Grid region
MISO (Midcontinent)
Utility / transmission owner
American Transmission Co.
Connection point (POI)
Chandler 138 kV Substation
Location
Delta County, Michigan
Technology
Solar: 125 MW
Total requested
125 MW
Service type
Network resource (NRIS)
Study phase
Study Phase: GIA; Post GIA Status: Withdrawn
Queue status
Withdrawn
Entered queue
16 June 2017
Agreement signed
26 June 2019
Proposed online date
April 2022
Withdrawn
April 2022

Location

Marker shows the centre of Delta County; the queue data does not give exact sites.

Power plants in Michigan Β· Transmission lines in Michigan

Other requests in Delta County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem