United States › Grid › Interconnection queues › Wyoming
OTHER · WESTOther project CLPT G16, Platte County
Other project CLPT G16, Platte County is a 300 MW other request with a signed interconnection agreement in the West interconnection queue, in Platte County, Wyoming, connecting to Black Hills Cheyenne Light Fuel and Power Transmission.
Queue statusConsented
- PlanningQueued Apr 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- CLPT G16
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Black Hills Cheyenne Light Fuel and Power Transmission
- Developer
- NextEra Energy Resources Interconnection Holdings, LLC
- Connection point (POI)
- Cheyenne - Windstar 230kV Line
- Location
- Platte County, Wyoming
- Technology
- Solar: 300 MW · Wind · Battery
- Total requested
- 300 MW
- Service type
- NRIS and ERIS
- Study phase
- LGIA Executed
- Queue status
- Active
- Entered queue
- 1 April 2022
- Proposed online date
- December 2025
Location
Marker shows the centre of Platte County; the queue data does not give exact sites.
Other requests in Platte County
- Solar + storage project GI-CS-2025-25, Platte CountySolar + storage · 800 MW · in study
- Other project 37681, Platte CountyOther · 200 MW · in study
- Other project 38047, Platte CountyOther · 200 MW · in study
- Solar project GI-TC-2024-03, Platte CountySolar · 160 MW · in study
- Onshore wind project GI-TC-2024-05, Platte CountyOnshore wind · 150 MW · in study
- Onshore wind project GI-TC-2024-06, Platte CountyOnshore wind · 150 MW · in study
- Onshore wind project GI-TC-2024-04, Platte CountyOnshore wind · 150 MW · in study
- Coal project GI-0511, Platte CountyCoal · 5.0 MW · built
- Pathfinder Renewable Wind EnergyOnshore wind · 3,000 MW · withdrawn
- Onshore wind project 927, Platte CountyOnshore wind · 600 MW · withdrawn
- Onshore wind project 931, Platte CountyOnshore wind · 400 MW · withdrawn
- Onshore wind project 932, Platte CountyOnshore wind · 400 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem