SOLAR + STORAGE · WEST

Solar + storage project GI-CS-2025-25, Platte County

Solar + storage project GI-CS-2025-25, Platte County is a 800 MW solar + storage request in interconnection study in the West interconnection queue, in Platte County, Wyoming, connecting to Tri-State Generation and Transmission Association.

Queue statusIn planning
  1. PlanningQueued Oct 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2030 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-CS-2025-25
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tri-State Generation and Transmission Association
Connection point (POI)
Laramie River 345kV Substation
Location
Platte County, Wyoming
Technology
Solar: 800 MW · Battery
Total requested
800 MW
Service type
Energy only (ERIS)
Study phase
Cluster Study
Queue status
Active
Entered queue
2 October 2025
Proposed online date
December 2030

Location

Marker shows the centre of Platte County; the queue data does not give exact sites.

Power plants in Wyoming · Transmission lines in Wyoming

Other requests in Platte County