Solar project GI-TC-2024-03, Platte County

Solar project GI-TC-2024-03, Platte County is a 160 MW solar request in interconnection study in the West interconnection queue, in Platte County, Wyoming, connecting to Tri-State Generation and Transmission Association.

Queue statusIn planning
  1. PlanningQueued May 2023 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2028 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
GI-TC-2024-03
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tri-State Generation and Transmission Association
Connection point (POI)
Monolith 115 kVSubstation
Location
Platte County, Wyoming
Technology
Solar: 160 MW
Total requested
160 MW
Service type
Energy only (ERIS)
Study phase
In Progress (unknown study)
Queue status
Active
Entered queue
8 May 2023
Proposed online date
December 2028

Location

Marker shows the centre of Platte County; the queue data does not give exact sites.

Power plants in Wyoming · Transmission lines in Wyoming

Other requests in Platte County