United States › Grid › Interconnection queues › Wyoming
OTHER · WESTOther project CLPT G17, Laramie County
Other project CLPT G17, Laramie County is a 300 MW other request with a signed interconnection agreement in the West interconnection queue, in Laramie County, Wyoming, connecting to Black Hills Cheyenne Light Fuel and Power Transmission.
Queue statusConsented
- PlanningQueued Apr 2022 (completed)
- Consented (current stage)
- Construction (not yet reached)
- OperatingTarget Dec 2025 (not yet reached)
- Closed (not yet reached)
Request details
- Queue ID
- CLPT G17
- Grid region
- West (non-ISO utilities)
- Utility / transmission owner
- Black Hills Cheyenne Light Fuel and Power Transmission
- Developer
- NextEra Energy Resources Interconnection Holdings, LLC
- Connection point (POI)
- East Business Park 115kV Substation
- Location
- Laramie County, Wyoming
- Technology
- Solar: 300 MW · Wind · Battery
- Total requested
- 300 MW
- Service type
- NRIS and ERIS
- Study phase
- LGIA Executed
- Queue status
- Active
- Entered queue
- 1 April 2022
- Proposed online date
- December 2025
Location
Marker shows the centre of Laramie County; the queue data does not give exact sites.
Other requests in Laramie County
- Solar + storage project CLPT G21, Laramie CountySolar + storage · 400 MW · agreement signed
- Onshore wind project GI-TC-2024-16, Laramie CountyOnshore wind · 400 MW · agreement signed
- Solar + storage project CLPT G20, Laramie CountySolar + storage · 365 MW · agreement signed
- Onshore wind project GI-TC-2024-15, Laramie CountyOnshore wind · 250 MW · agreement signed
- Onshore wind project CLPT G24, Laramie CountyOnshore wind · 200 MW · agreement signed
- Onshore wind project CLPT G23, Laramie CountyOnshore wind · 150 MW · agreement signed
- Gas project CLPT G22, Laramie CountyGas · 115 MW · agreement signed
- Gas project 37316, Laramie CountyGas · 600 MW · in study
- Onshore wind project 21-08242, Laramie CountyOnshore wind · 350 MW · in study
- Wind + storage project GI-CS-2025-04, Laramie CountyWind + storage · 330 MW · in study
- Wind + storage project 39873, Laramie CountyWind + storage · 198 MW · in study
- Other project CLPT G29, Laramie CountyOther · 150 MW · in study