United States › Grid › Interconnection queues › Wyoming

ONSHORE WIND · WEST

Onshore wind project GI-TC-2024-15, Laramie County

Onshore wind project GI-TC-2024-15, Laramie County is a 250 MW onshore wind request with a signed interconnection agreement in the West interconnection queue, in Laramie County, Wyoming, connecting to Tri-State Generation and Transmission Association.

Queue statusConsented
  1. PlanningQueued May 2024 (completed)
  2. Consented (current stage)
  3. Construction (not yet reached)
  4. OperatingTarget Sep 2029 (not yet reached)
  5. Closed (not yet reached)

Request details

Queue ID
GI-TC-2024-15
Grid region
West (non-ISO utilities)
Utility / transmission owner
Tri-State Generation and Transmission Association
Connection point (POI)
Big Bear 345kV Switching Station
Location
Laramie County, Wyoming
Technology
Wind: 250 MW
Total requested
250 MW
Service type
Energy only (ERIS)
Study phase
Executed LGIA
Queue status
Active
Entered queue
23 May 2024
Proposed online date
September 2029

Location

Marker shows the centre of Laramie County; the queue data does not give exact sites.

Power plants in Wyoming · Transmission lines in Wyoming

Other requests in Laramie County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem