United States โ€บ Grid โ€บ Interconnection queues โ€บ Virginia

OCTARY USA ยท INTERCONNECTION QUEUES

Battery storage interconnection queue in Virginia

Before a new power plant or battery can connect to the US grid, it joins a queue for studies and an interconnection agreement. Most requests never get built. This shows every request: active, built and withdrawn.

Requests shown979,916 MW
Active in queue9,916 MW97 requests
Agreement signed793 MW10 requests
Withdrawn18614.7 GW never built

Map

Loading requestsโ€ฆ
In studyAgreement signedUnder constructionBuiltSuspendedWithdrawn

Requests

97 requests ยท page 1 of 2
ProjectCapacityStatusLocationRegionQueuedOnline
Battery storage project AH1-716, James City County
Battery storage ยท Cardinal Energy Storage East, LLC
650 MWIn study James City, VAPJM Apr 2025
Battery storage project AH1-727, Loudoun County
Battery storage ยท Cardinal Energy Storage East, LLC
425 MWIn study Loudoun, VAPJM Apr 2025
Battery storage project AH2-133, City Of Chesapeake County
Battery storage
300 MWIn study City Of Chesapeake, VAPJM Mar 2022target 2027
Battery storage project AI1-017, Surry County
Battery storage
300 MWIn study Surry, VAPJM Apr 2022target 2026
Battery storage project AI1-018, Spotsylvania County
Battery storage
300 MWIn study Spotsylvania, VAPJM Apr 2022target 2026
Battery storage project AG2-360, Smyth County
Battery storage ยท Laurel Creek Energy Storage LLC
250 MWIn study Smyth, VAPJM Feb 2025target 2024
Battery storage project AI1-185, Augusta County
Battery storage
210 MWIn study Augusta, VAPJM Sep 2022target 2027
Prospect Power
Battery storage
200 MWAgreement signed Rockingham, VAPJM May 2019target 2026
Battery storage project AH2-102, Franklin County
Battery storage
200 MWIn study Franklin, VAPJM Jan 2022target 2026
Battery storage project AH1-263, Spotsylvania County
Battery storage ยท Scarlet Energy Storage LLC
200 MWIn study Spotsylvania, VAPJM Feb 2025target 2025
Battery storage project AI1-013, Charles City County
Battery storage
200 MWIn study Charles City, VAPJM Apr 2022target 2026
Battery storage project AI2-045, City Of Virginia Beach County
Battery storage
150 MWIn study City Of Virginia Beach, VAPJM Feb 2023target 2023
Battery storage project AI2-456, King George County
Battery storage
150 MWIn study King George, VAPJM Mar 2023target 2027
Battery storage project AI2-001, Caroline County
Battery storage
150 MWIn study Caroline, VAPJM Oct 2022target 2028
Battery storage project AG2-288, Frederick County
Battery storage ยท Rockline Reliability Center LLC
150 MWIn study Frederick, VAPJM Feb 2025target 2023
Battery storage project AI2-002, Washington County
Battery storage
150 MWIn study Washington, VAPJM Oct 2022target 2028
Battery storage project AH2-144, King George County
Battery storage
150 MWIn study King George, VAPJM Feb 2022target 2027
Battery storage project AI2-044, City Of Virginia Beach County
Battery storage
150 MWIn study City Of Virginia Beach, VAPJM Feb 2023target 2023
Battery storage project AH2-291, Brunswick County
Battery storage
150 MWIn study Brunswick, VAPJM Mar 2022target 2026
Battery storage project AG2-088, Chesterfield County
Battery storage ยท Hermon Energy Center, LLC
150 MWIn study Chesterfield, VAPJM Feb 2025target 2022
Battery storage project AG2-270, Halifax County
Battery storage ยท Clover Storage, LLC
150 MWIn study Halifax, VAPJM Apr 2025target 2025
Battery storage project AI1-186, Shenandoah County
Battery storage
140 MWIn study Shenandoah, VAPJM Sep 2022target 2027
Battery storage project AH2-083, Caroline County
Battery storage
140 MWIn study Caroline, VAPJM Jan 2022target 2027
Battery storage project AI1-183, Richmond County
Battery storage
130 MWIn study Richmond, VAPJM Sep 2022target 2027
Battery storage project AH2-084, Fauquier County
Battery storage
125 MWIn study Fauquier, VAPJM Jan 2022target 2027
Battery storage project AI2-230, Caroline County
Battery storage
120 MWIn study Caroline, VAPJM Mar 2023target 2023
Battery storage project AI2-231, Prince William County
Battery storage
120 MWIn study Prince William, VAPJM Mar 2023target 2023
New Road Storage
Battery storage
120 MWAgreement signed Loudoun, VAPJM Dec 2018target 2027
Battery storage project AI1-184, Frederick County
Battery storage
110 MWIn study Frederick, VAPJM Sep 2022target 2027
Battery storage project AH2-246, Prince George County
Battery storage
100 MWIn study Prince George, VAPJM Mar 2022target 2025
Battery storage project AI2-114, Augusta County
Battery storage
100 MWIn study Augusta, VAPJM Mar 2023target 2029
Battery storage project AJ1-019, Southampton County
Battery storage
100 MWIn study Southampton, VAPJM Jun 2023target 2028
Battery storage project AI2-005, Fluvanna County
Battery storage
100 MWIn study Fluvanna, VAPJM Oct 2022target 2028
Harwood Power
Battery storage
100 MWAgreement signed King George, VAPJM Oct 2019target 2029
Battery storage project AJ1-003, Mecklenburg County
Battery storage
100 MWIn study Mecklenburg, VAPJM Apr 2023target 2028
Battery storage project AH2-034, Prince William County
Battery storage
100 MWIn study Prince William, VAPJM Nov 2021target 2028
Battery storage project AJ1-002, Rockingham County
Battery storage
100 MWIn study Rockingham, VAPJM Apr 2023target 2028
Battery storage project AH2-330, City Of Chesapeake County
Battery storage
100 MWIn study City Of Chesapeake, VAPJM Mar 2022target 2027
Battery storage project AH2-035, Prince William County
Battery storage
100 MWIn study Prince William, VAPJM Nov 2021target 2028
Battery storage project AG2-300, Frederick County
Battery storage ยท Meadow Brook Storage, LLC
100 MWIn study Frederick, VAPJM Feb 2025target 2023
Battery storage project AH2-378, Prince George County
Battery storage
100 MWIn study Prince George, VAPJM Mar 2022target 2025
Battery storage project AI2-039, Surry County
Battery storage
100 MWIn study Surry, VAPJM Feb 2023target 2026
Yadkins Energy Center
Battery storage ยท Yadkins Energy Center, LLC
100 MWIn study City Of Chesapeake, VAPJM Mar 2019target 2021
Battery storage project AH1-314, Pittsylvania County
Battery storage ยท Pittsylvania Energy Storage LLC
100 MWIn study Pittsylvania, VAPJM Feb 2025target 2025
Battery storage project AG2-571, Brunswick County
Battery storage ยท Zeus Storage, LLC
100 MWIn study Brunswick, VAPJM Mar 2025target 2024
Battery storage project AI1-102, City Of Suffolk County
Battery storage
100 MWIn study City Of Suffolk, VAPJM Aug 2022target 2029
Remington BESS
Battery storage
100 MWAgreement signed Fauquier, VAPJM Sep 2020target 2029
Battery storage project AI1-089, City Of Suffolk County
Battery storage
100 MWIn study City Of Suffolk, VAPJM Jul 2022target 2025
Battery storage project AG2-339, Sussex County
Battery storage ยท Cassius Blue Solar LLC
85.0 MWIn study Sussex, VAPJM Apr 2025target 2024
Battery storage project AH1-461, Tazewell County
Battery storage ยท Lakeside Energy, LLC
80.0 MWIn study Tazewell, VAPJM Feb 2025target 2024
Page 1 of 2

Source: Rand, J. et al., Queued Up, Lawrence Berkeley National Laboratory, data through end of 2025. Compiled from the queues of the 7 ISO/RTOs and dozens of non-ISO utilities. A request is a proposal to connect, not a commitment to build: historically most are withdrawn. Capacity is the requested interconnection size; hybrids include the storage component. Transmission lines ยท Planned power plants (EIA)