Battery storage project AG2-300, Frederick County

Battery storage project AG2-300, Frederick County is a 100 MW battery storage request in interconnection study in the PJM interconnection queue, in Frederick County, Virginia, connecting to APS.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2023 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-300
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Developer
Meadow Brook Storage, LLC
Connection point (POI)
Meadow Brook 138 kV
Location
Frederick County, Virginia
Technology
Battery: 100 MW
Total requested
100 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
5 February 2025
Proposed online date
December 2023

Location

Marker shows the centre of Frederick County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Frederick County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem