United States › Grid › Interconnection queues › Virginia

SOLAR · PJM

Foxglove Solar

Foxglove Solar is a 75.0 MW solar request built and operating in the PJM interconnection queue, in Frederick County, Virginia, connecting to APS.

Queue statusOperating
  1. PlanningQueued Oct 2017 (completed)
  2. ConsentedAug 2021 (completed)
  3. Construction (completed)
  4. OperatingOct 2024 (current stage)
  5. Closed (not yet reached)

Request details

Queue ID
AD1-155
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
APS
Connection point (POI)
Meadow Brook-Strasburg 138 kV
Location
Frederick County, Virginia
Technology
Solar: 75.0 MW
Total requested
75.0 MW
Service type
Network resource (NRIS)
Study phase
Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
Queue status
Operational
Entered queue
2 October 2017
Agreement signed
11 August 2021
Proposed online date
June 2024
Came online
October 2024

Location

Marker shows the centre of Frederick County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Frederick County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem