United States βΊ Grid βΊ Interconnection queues βΊ Virginia
SOLAR Β· PJMSolar project AH1-001, Frederick County
Solar project AH1-001, Frederick County is a 50.0 MW solar request withdrawn in the PJM interconnection queue, in Frederick County, Virginia, connecting to APS.
Queue statusWithdrawn / abandoned
- PlanningQueued Apr 2021 (completed)
- Withdrawn / abandonedDec 2024 (project stopped here)
- Consented (not reached)
- Construction (not reached)
- Operating (not reached)
- Closed (not reached)
Request details
- Queue ID
- AH1-001
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Bartonsville-Meadowbrook 138 kV
- Location
- Frederick County, Virginia
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Feasibility Study
- Queue status
- Withdrawn
- Entered queue
- 1 April 2021
- Proposed online date
- December 2023
- Withdrawn
- December 2024
Location
Marker shows the centre of Frederick County; the queue data does not give exact sites.
Other requests in Frederick County
- Solar project AG2-182, Frederick CountySolar Β· 200 MW Β· in study
- Battery storage project AG2-288, Frederick CountyBattery storage Β· 150 MW Β· in study
- Battery storage project AI1-184, Frederick CountyBattery storage Β· 110 MW Β· in study
- Battery storage project AG2-300, Frederick CountyBattery storage Β· 100 MW Β· in study
- Redbud-Gaylord 34.5 kVSolar Β· 30.0 MW Β· suspended
- Foxglove SolarSolar Β· 75.0 MW Β· built
- Bartonsville Energy FacilitySolar Β· 70.0 MW Β· built
- Bartonsville Energy FacilitySolar Β· 50.0 MW Β· built
- Bartonsville Energy FacilitySolar Β· 10.0 MW Β· built
- Fredrick County Regional LFOther Β· 2.0 MW Β· built
- Solar + storage project AH1-119, Frederick CountySolar + storage Β· 100 MW Β· withdrawn
- Solar + storage project AG2-584, Frederick CountySolar + storage Β· 90.0 MW Β· withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem