Solar project AG2-182, Frederick County

Solar project AG2-182, Frederick County is a 200 MW solar request in interconnection study in the PJM interconnection queue, in Frederick County, Virginia, connecting to Dominion.

Queue statusIn planning
  1. PlanningQueued Feb 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2022 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-182
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Developer
ACE Development Company, LLC
Connection point (POI)
Doubs-Bismark 500 kV
Location
Frederick County, Virginia
Technology
Solar: 200 MW
Total requested
200 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
25 February 2025
Proposed online date
December 2022

Location

Marker shows the centre of Frederick County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Frederick County