SOLAR · PJMBartonsville Energy Facility
Bartonsville Energy Facility is a 50.0 MW solar request built and operating in the PJM interconnection queue, in Frederick County, Virginia, connecting to APS.
Request details
- Queue ID
- AF2-075
- Grid region
- PJM (Mid-Atlantic, Midwest)
- Utility / transmission owner
- APS
- Connection point (POI)
- Bartonsville-Meadow Brook 138 kV III
- Location
- Frederick County, Virginia
- Technology
- Solar: 50.0 MW
- Total requested
- 50.0 MW
- Service type
- Network resource (NRIS)
- Study phase
- Available studies: Feasibility Study, System Impact Study, Facilities Study; Interim/Interconnection Service Agreement:
- Queue status
- Operational
- Entered queue
- 1 February 2020
- Proposed online date
- July 2024
- Came online
- December 2024
Location
Marker shows the centre of Frederick County; the queue data does not give exact sites.
Other requests in Frederick County
- Solar project AG2-182, Frederick CountySolar · 200 MW · in study
- Battery storage project AG2-288, Frederick CountyBattery storage · 150 MW · in study
- Battery storage project AI1-184, Frederick CountyBattery storage · 110 MW · in study
- Battery storage project AG2-300, Frederick CountyBattery storage · 100 MW · in study
- Redbud-Gaylord 34.5 kVSolar · 30.0 MW · suspended
- Foxglove SolarSolar · 75.0 MW · built
- Bartonsville Energy FacilitySolar · 70.0 MW · built
- Bartonsville Energy FacilitySolar · 10.0 MW · built
- Fredrick County Regional LFOther · 2.0 MW · built
- Solar + storage project AH1-119, Frederick CountySolar + storage · 100 MW · withdrawn
- Solar + storage project AG2-584, Frederick CountySolar + storage · 90.0 MW · withdrawn
- Solar project AH1-001, Frederick CountySolar · 50.0 MW · withdrawn
Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem