🔌 EV Partnership Switch to Octopus Energy & unlock exclusive smart EV charging rates Find out more → Skip to main content

United States › Grid › Interconnection queues › Virginia

BATTERY STORAGE · PJM

Battery storage project AG2-270, Halifax County

Battery storage project AG2-270, Halifax County is a 150 MW battery storage request in interconnection study in the PJM interconnection queue, in Halifax County, Virginia, connecting to Dominion.

Queue statusIn planning
  1. PlanningQueued Apr 2025 (current stage)
  2. Consented (not yet reached)
  3. Construction (not yet reached)
  4. OperatingTarget Dec 2025 (not yet reached)
  5. Closed (not yet reached)

Studies assess what grid upgrades the project would need and who pays for them. A signed interconnection agreement is the main step before construction.

Request details

Queue ID
AG2-270
Grid region
PJM (Mid-Atlantic, Midwest)
Utility / transmission owner
Dominion
Developer
Clover Storage, LLC
Connection point (POI)
Clover 230 kV
Location
Halifax County, Virginia
Technology
Battery: 150 MW
Total requested
150 MW
Service type
Network resource (NRIS)
Study phase
System Impact Study
Queue status
Active
Entered queue
2 April 2025
Proposed online date
December 2025

Location

Marker shows the centre of Halifax County; the queue data does not give exact sites.

Power plants in Virginia · Transmission lines in Virginia

Other requests in Halifax County

Source: Lawrence Berkeley National Laboratory, Queued Up, data through end of 2025, compiled from ISO/RTO and utility queues. Check the grid operator's own queue for the latest status. Report a problem